Construction Timeline for a Typical G+1 or G+2 Home

How long each stage of an independent home really takes — excavation to handover — with the durations we plan for, what commonly slips, and how monsoon affects the schedule.

Garden-side elevation of a completed two-storey home

Homeowners are usually told "10 to 12 months". That is a fair number for a G+1 home on a straightforward plot — but only if the design is frozen, the drawings exist and materials arrive on time. Below is the stage-by-stage schedule we plan against, followed by the things that stretch it.

Indicative schedule

StageG+1 (≈ 2,000 sq.ft)G+2 (≈ 3,000 sq.ft)Depends on
Mobilisation, layout, excavation1–2 weeks1–2 weeksAccess, soil
Footings and columns to plinth3–4 weeks4–5 weeksFooting type, curing
Plinth beam, filling, DPC2 weeks2 weeksFill availability
Each floor: columns, beams, slab4–5 weeks per floor4–5 weeks per floorFormwork cycle, curing (min. 7 days before striking props partially)
Masonry and lintels, all floors4–6 weeks6–8 weeksBlock type, labour
Conduits, plumbing rough-in, plaster5–7 weeks7–9 weeksLayout approvals
Waterproofing and services3–4 weeks4–5 weeksPonding tests
Flooring, doors, windows5–7 weeks7–9 weeksMaterial lead times
Painting, fixtures, snagging, handover4–5 weeks5–6 weeksDecision speed
Total9–12 months12–15 months

What usually slips

  • Design decisions taken late. Tile, sanitaryware and window selections have 3–6 week lead times; if they are chosen after plaster, the site waits.
  • Curing shortcuts. Striking slab formwork early to save days causes deflection and cracks; we do not compress this stage.
  • Monsoon. In Pune, June–September slows excavation and external work; plan foundations for October–May where possible, and superstructure can continue under cover.
  • Approvals and connections. Utility connections can take longer than the finishing they wait for.